CUP: J37H14001030006
RIORDINO DEL SISTEMA DI RACCOLTA E DEPURAZIONE DEGLI AGGLOMERATI DI CORCIANO MEDIANTE RACCOLTA DELLE RETI FOGNARIE ESISTENTI E COLLETTAMENTO VERSO IL DEPURATORE DI TAVERNE NEL COMUNE DI CORCIANO RACCOGLIENDO PARTE DI S. MARIANO, TERRIOLI E SOLOMEO.
SUMMARY OF THE PROJECT
RIORDINO DEL SISTEMA DI RACCOLTA E DEPURAZIONE DEGLI AGGLOMERATI DI CORCIANO MEDIANTE RACCOLTA DELLE RETI FOGNARIE ESISTENTI E COLLETTAMENTO VERSO IL DEPURATORE DI TAVERNE NEL COMUNE DI CORCIANO RACCOGLIENDO PARTE DI S. MARIANO, TERRIOLI E SOLOMEO.
Implementation indicator
Ampliamento lunghezza rete
- Target
- 8,250 m
- Achieved
- 7,231 m
Download project
Funding monitored
€ 1,364,651.40
of which cohesion funds
€ 1,214,651.40
Given name | Amount |
---|---|
Development and Cohesion Fund | 1214651.40 |
Another public source | 150000.00 |
Payments monitored
€ 1,364,651.40
of which cohesion funds
€ 1,214,651.40
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 16827.44 | 16827.44 | 1 |
2015 | 43478.72 | 60306.16 | 4 |
2016 | 54475.42 | 114781.58 | 8 |
2017 | 919405.57 | 1034187.15 | 75 |
2018 | 330464.25 | 1364651.40 | 100 |
State of progress
Completed
Expected start: 02/05/2016
Effective start: 09/05/2016
Expected end: 31/12/2017
Effective end: 28/12/2017
Entities
- Planning body
- REGIONE UMBRIA
- Beneficiary
- UMBRA ACQUE SPA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE UMBRIA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche