CUP: G47H15000610007
RISANAMENTO E MANUTENZIONE DELLA STRADA RURALE INCROCIO GUGGENBERG FINO MUDLER
SUMMARY OF THE PROJECT
RISANAMENTO E MANUTENZIONE DELLA STRADA RURALE INCROCIO GUGGENBERG FINO MUDLER
Implementation indicator
Estensione in lunghezza
- Target
- 1.59 km
- Achieved
- 1.59 km
Download project
Funding monitored
€ 127,856.00
of which cohesion funds
€ 127,856.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 127856.00 |
- Other resources - Private:
- € 31,964
Payments monitored
€ 127,856.00
of which cohesion funds
€ 127,856.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 51142.40 | 51142.40 | 40 |
2016 | 0 | 51142.40 | 40 |
2017 | 76713.60 | 127856.00 | 100 |
State of progress
Completed
Expected start: 29/07/2015
Effective start: 29/07/2015
Expected end: 22/12/2017
Effective end: 02/06/2017
Entities
- Planning body
- PROVINCIA AUTONOMA DI BOLZANO
- Implementing body
- CONSORZIO DI BONIFICA VALLE DI CASIES-TESIDO/BERGBONIFIZIERUNGSKONSORTIUM GSIES-TAISTEN
- Beneficiary
- PROVINCIA AUTONOMA DI BOLZANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC P.A. BOLZANO
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale