CUP: J36J15000540001
Micronidi e Nidi Ambito S10
Download project
Funding monitored
€ 65,107.74
of which cohesion funds
€ 65,107.74
Given name | Amount |
---|---|
Revolving Fund (Cohesion Action Plan) | 65107.74 |
- Economies:
- € 25,964.03
Payments monitored
€ 65,107.74
of which cohesion funds
€ 65,107.74
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 65107.74 | 65107.74 | 100 |
State of progress
Completed
Expected start: 01/01/2015
Effective start: 18/04/2016
Expected end: 30/06/2018
Effective end: 23/11/2016
Type
- Procurement of goods and services
- NUOVA FORNITURA
Theme
- Social inclusion and health
- Servizi per l'infanzia - Sostegno alla domanda e alla gestione (solo nidi)
Territory
Entities
- Planning body
- MINISTERO DELL'INTERNO - AUTORITA DI GESTIONE PROGRAMMA NAZIONALE SERVIZI DI CURA ALLINFANZIA E AGLI ANZIANI NON AUTOSUFFICIENTI
- Implementing body
- COMUNE DI SALA CONSILINA
- Beneficiary
- COMUNE DI SALA CONSILINA
- Executor
- NEW FONTANILI SRL
- Priority QSN
- Inclusione sociale e servizi per la qualità della vita e l'attrattività territoriale
- General objective QSN
- Servizi di cura per l'infanzia
- Specific objective QSN
- Miglioramento della qualità e della gestione dei servizi socioeducativi
Programming area
- Programme
- PROGRAMMA PAC MINISTERO DELL'INTERNO - PIANO NAZIONALE SERVIZI DI CURA
- 2007-2013 Cohesion Action Plan
- 2007-2013 Cohesion Action Plan
- Cohesion funds
- € 65,107.74
- Payments on cohesion funds
- € 65,107.74
- Line
- Servizi di cura per l'infanzia
- Action
- Infanzia - Secondo riparto per Ambito