CUP: B35B17000770001
PATTO CITTA' DI GENOVA EX CASERMA GAVOGLIO - PARCO VALLETTA CINQUE SANTI
SUMMARY OF THE PROJECT
DEMOLIZIONE DI ALCUNI EDIFICI DISMESSI E LA SISTEMAZIONE DELLE SUPERFICI A PARCO, PRIVILEGIANDO L'IMPIEGO DI TECNICHE NATURALI - INGEGNERIA NATURALISTICA, ACCUMULO DI ACQUE METEORICHE, PAVIMNETAZIONI DRENANTI, ETC.
Implementation indicator
Superficie oggetto di intervento
- Target
- 14,900 mq
- Achieved
- 0 mq
Download project
Funding monitored
€ 3,743,000.00
of which cohesion funds
€ 3,743,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3743000.00 |
Payments monitored
€ 3,446,527.42
of which cohesion funds
€ 3,446,527.42
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 45846.24 | 45846.24 | 1 |
2019 | 726300.67 | 772146.91 | 20 |
2020 | 371196.13 | 1143343.04 | 30 |
2021 | 495576.59 | 1638919.63 | 43 |
2022 | 1315512.27 | 2954431.90 | 78 |
2023 | 367856.18 | 3322288.08 | 88 |
2024 | 124239.34 | 3446527.42 | 92 |
State of progress
Open
Expected start: 01/11/2019
Effective start: 02/12/2019
Expected end: 31/07/2021
Effective end: not available
Entities
- Planning body
- COMUNE DI GENOVA
- Implementing body
- COMUNE DI GENOVA
- Beneficiary
- COMUNE DI GENOVA
Programming area
- Programme
- PSC CITTA' METROPOLITANA DI GENOVA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 3,743,000.00
- Payments on cohesion funds
- € 3,446,527.42
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici