Updated on 31/12/2020
Funding monitored € 388,522.07 of which cohesion funds € 388,522.07
Given name Amount
European Union291391.55
Revolving Fund (National co-financing)97130.52
Payments monitored € 388,522.07 of which cohesion funds € 388,522.07
Year Amount Cumulative amount Percentage on public financing
2014324145.59324145.5983
201566335.78390481.37100
20160390481.37100
2017-1959.30388522.07100

State of progress

Completed
Expected start: 08/07/2013
Effective start: 08/07/2013
Expected end: 16/07/2014
Effective end: 16/07/2014

Type

Theme

  • Energy
  • Efficienza dell'energia, cogenerazione, gestione dell'energia

Territory

Entities

Planning body
MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
Implementing body
COMUNE DI BAGNARA CALABRA
Beneficiary
MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
Specific objective QSN
Promozione dell'efficienza energetica e del risparmio dell'energia

Programming area

Programme
IROP CONV ERDF RENEWABLE ENERGY AND ENERGY CONSERVATION
European Regional Development Fund (ERDF)
2007-2013 EU Structural Funds
Cohesion funds
€ 388,522.07
Payments on cohesion funds
€ 388,522.07
Axis
Asse II Efficienza energetica ed ottimizzazione del sistema
Operational objective
Sperimentare e realizzare forme avanzate di interventi di efficientamento energetico su edifici e utenze pubbliche.

Other projects in territory