CUP: B14C07000040003
Rete telematica provincialeCollegamento SS49 - Fortezza
SUMMARY OF THE PROJECT
Rete telematica provincialeCollegamento SS49 - Fortezza
Implementation indicator
Estensione dell'intervento in lunghezza
- Target
- 6,855 m
- Achieved
- 6,855 m
Download project
Funding monitored
€ 501,024.66
of which cohesion funds
€ 501,024.66
Given name | Amount |
---|---|
Development and Cohesion Fund | 501024.66 |
Payments monitored
€ 501,024.66
of which cohesion funds
€ 501,024.66
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 3494.40 | 3494.40 | 0 |
2008 | 270729.10 | 274223.50 | 54 |
2009 | 187858.34 | 462081.84 | 92 |
2010 | 38942.82 | 501024.66 | 100 |
State of progress
Completed
Expected start: 16/05/2008
Effective start: 16/05/2008
Expected end: 29/05/2009
Effective end: 29/05/2009
Entities
- Planning body
- PROVINCIA AUTONOMA DI BOLZANO
- Implementing body
- PROVINCIA AUTONOMA DI BOLZANO
- Beneficiary
- PROVINCIA AUTONOMA DI BOLZANO
Programming area
- Programme
- PSC P.A. BOLZANO
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 501,024.66
- Payments on cohesion funds
- € 501,024.66
- Policy Area
- Digitalizzazione
- Sector of intervention
- Connettivita' digitale