CUP: D47H17000250001
SP N 32 DEL BOCCO DI LEIVI LAVORI DI SISTEMAZIONE DEL PONTE MAGGI IN COMUNE DI SAN COLOMBANO CERTENOLI
SUMMARY OF THE PROJECT
LAVORI DI SISTEMAZIONE DEL PONTE MAGGI SULLA STRADA PROVINCIALE N 32 DI BOCCO DI LEIVI IN COMUNE DI SAN COLOMBANO CERTENOLI
Implementation indicator
Estensione dell'intervento in lunghezza
- Target
- 110 m
- Achieved
- 110 m
Funding monitored
€ 500,582.90
of which cohesion funds
€ 500,582.90
Given name | Amount |
---|---|
Development and Cohesion Fund | 500582.90 |
- Economies:
- € 134,417.10
Payments monitored
€ 500,582.90
of which cohesion funds
€ 500,582.90
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 38796.00 | 38796.00 | 7 |
2019 | 8710.80 | 47506.80 | 9 |
2020 | 359456.34 | 406963.14 | 81 |
2021 | 87347.12 | 494310.26 | 98 |
2022 | 0 | 494310.26 | 98 |
2023 | 6272.64 | 500582.90 | 100 |
State of progress
Completed
Expected start: 31/05/2020
Effective start: 20/07/2020
Expected end: 30/03/2021
Effective end: 02/03/2021
Entities
- Planning body
- COMUNE DI GENOVA
- Implementing body
- CITTA METROPOLITANA DI GENOVA
- Beneficiary
- CITTA METROPOLITANA DI GENOVA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC CITTA' METROPOLITANA DI GENOVA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico