CUP: D37H18001990002
01IRA54/G1-SP 78 ¿ LAVORI DI MESSA IN SICUREZZA TRATTI DI VERSANTE ATTRAVERSO MEDIANTE INTERVENTI DI DIFESA ATTIVA E PASSIVA¿ I LOTTO
SUMMARY OF THE PROJECT
INTERVENTI DI MANUTENZIONE ORDINARIA E STRAORDINARIA DEL TERRITORIO MIRATI ALLA RIDUZIONE DEL RISCHIO IDROGEOLOGICO DIFFUSO SULLA VIABILITÃ DELLA PROVINCIA DI VERCELLI NEI COMUNI DI FOBELLO, ROSSA, VARALLO E CIVIASCO.
Implementation indicator
Popolazione beneficiaria di misure di protezione contro le alluvioni
- Target
- 10 num
- Achieved
- 10 num
Download project
Funding monitored
€ 500,000.00
of which cohesion funds
€ 500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 500000.00 |
Payments monitored
€ 466,090.38
of which cohesion funds
€ 466,090.38
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 29712.88 | 29712.88 | 5 |
2022 | 435025.73 | 464738.61 | 92 |
2023 | 1351.77 | 466090.38 | 93 |
State of progress
Open
Expected start: 13/09/2021
Effective start: 20/12/2021
Expected end: 11/10/2021
Effective end: 05/07/2022
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA TUTELA DEL TERRITORIO E DEL MARE-DIREZIONE GENERALE PER LA SALVAGUARDIA DEL TERRITORIO E DELLE ACQUE
- Implementing body
- COMMISSARIO DI GOVERNO CONTRO IL DISSESTO IDROGEOLOGICO REGIONE PIEMONTE
- Beneficiary
- COMMISSARIO DI GOVERNO CONTRO IL DISSESTO IDROGEOLOGICO REGIONE PIEMONTE
- Executor
-
RAGGRUPPAMENTO TEMPORANEO M.B.G. DI MASONI BOTTONI GIULIANO (MANDATARIA) / BERTINI S.R.L.
AMMINISTRAZIONE PROVINCIALE DI VERCELLI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico