CUP: H26B19001510004
Torrente Aurino: costruzione di opere di difesa
SUMMARY OF THE PROJECT
Torrente Aurino: costruzione di opere di difesa
Implementation indicator
Popolazione beneficiaria di misure di protezione contro le alluvioni
- Target
- 147 num
- Achieved
- 0 num
Download project
Funding monitored
€ 500,000.00
of which cohesion funds
€ 500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 500000.00 |
Payments monitored
€ 498,612.69
of which cohesion funds
€ 498,612.69
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 40598.94 | 40598.94 | 8 |
2022 | 216803.08 | 257402.02 | 51 |
2023 | 219070.06 | 476472.08 | 95 |
2024 | 22094.97 | 498567.05 | 99 |
2025 | 45.64 | 498612.69 | 99 |
State of progress
Settled
Expected start: 01/06/2021
Effective start: 01/06/2021
Expected end: 31/05/2025
Effective end: not available
Entities
Programming area
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 500,000.00
- Payments on cohesion funds
- € 498,612.69
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico