CUP: D36J17000200001
Consolidamento e regimentazione delle acque area limtrofa alla chiesa di San Giuseppe
SUMMARY OF THE PROJECT
Consolidamento e regimentazione delle acque - Completamento e messa in sicurezza area limtrofa alla chiesa di San Giuseppe
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 50 num
- Achieved
- 0 num
Download project
Funding monitored
€ 999,935.36
of which cohesion funds
€ 999,935.36
Given name | Amount |
---|---|
Development and Cohesion Fund | 999935.36 |
Payments monitored
€ 102,393.38
of which cohesion funds
€ 102,393.38
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 28547.88 | 28547.88 | 2 |
2022 | 38891.21 | 67439.09 | 6 |
2023 | 0 | 67439.09 | 6 |
2024 | 34954.29 | 102393.38 | 10 |
State of progress
Open
Expected start: 03/06/2024
Effective start: 31/07/2023
Expected end: 31/05/2025
Effective end: not available
Entities
- Planning body
- Ministero dell'Ambiente e della Tutela del Territorio e del Mare-Direzione Generale per la Salvaguardia del Territorio e delle Acque
- Implementing body
- STRUTTURA COMMISSARIALE STRAORD.DELEGATA ALLA REALIZZAZIONE DEGLI INTERVENTI DI MITIGAZIONE DEL RISCHIO IDROGEOLOGICO PER LA REG. MOLISE
- Beneficiary
- STRUTTURA COMMISSARIALE STRAORD.DELEGATA ALLA REALIZZAZIONE DEGLI INTERVENTI DI MITIGAZIONE DEL RISCHIO IDROGEOLOGICO PER LA REG. MOLISE
- Executor
- SPINA MICHELE S.R.L.
Programming area
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 999,935.36
- Payments on cohesion funds
- € 102,393.38
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico