CUP: J17B17000100009
Lavori di consolidamento Via XXIV Maggio
SUMMARY OF THE PROJECT
Costruzione diaframma mediante collegati con trave tirantata in c.a. e sormontata da parete in c.a.
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 1,200 num
- Achieved
- 0 num
Download project
Funding monitored
€ 2,300,000.00
of which cohesion funds
€ 2,300,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 2300000.00 |
Payments monitored
€ 162,689.24
of which cohesion funds
€ 162,689.24
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 6480.21 | 6480.21 | 0 |
2020 | 55321.98 | 61802.19 | 2 |
2021 | 0 | 61802.19 | 2 |
2022 | 62176.04 | 123978.23 | 5 |
2023 | 38711.01 | 162689.24 | 7 |
State of progress
Open
Expected start: 20/09/2024
Effective start: 29/08/2024
Expected end: 30/09/2025
Effective end: not available
Entities
- Planning body
- Ministero dell'Ambiente e della Tutela del Territorio e del Mare-Direzione Generale per la Salvaguardia del Territorio e delle Acque
- Implementing body
- COMMISSARIO STRAORDINARIO PER L'ATTUAZIONE DEGLI INTERVENTI PER LA MITIGAZIONE DEL RISCHIO IDROGEOLOGICO NELLA REGIONE PUGLIA
- Beneficiary
- COMMISSARIO STRAORDINARIO PER L'ATTUAZIONE DEGLI INTERVENTI PER LA MITIGAZIONE DEL RISCHIO IDROGEOLOGICO NELLA REGIONE PUGLIA
- Executor
-
Unyon Consorzio Stabile scarl
PLANETEK ITALIA SRL
LEXMEDIA SRL
ING. LOBEFARO ANGELO
ING. CARBONE FILOMENA
Programming area
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 2,300,000.00
- Payments on cohesion funds
- € 162,689.24
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico