Consolidamento e messa in sicurezza centro urbano in località Circumvallazione
SUMMARY OF THE PROJECT
Realizzazione di un muro su doppia fila di micropali, interventi di minimizzazione e forestazione ovvero di ingegneria naturalistica
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 1,000 num
- Achieved
- 0 num
Download project
Funding monitored
€ 2,770,000.00
of which cohesion funds
€ 2,770,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 2770000.00 |
Payments monitored
€ 542,543.63
of which cohesion funds
€ 542,543.63
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 7772.49 | 7772.49 | 0 |
2020 | 59688.84 | 67461.33 | 2 |
2021 | 1244.81 | 68706.14 | 2 |
2022 | 0 | 68706.14 | 2 |
2023 | 0 | 68706.14 | 2 |
2024 | 473837.49 | 542543.63 | 19 |
State of progress
Open
Expected start: 01/04/2025
Effective start: not available
Expected end: 30/09/2025
Effective end: not available
Entities
- Planning body
- Ministero dell'Ambiente e della Tutela del Territorio e del Mare-Direzione Generale per la Salvaguardia del Territorio e delle Acque
- Implementing body
- COMMISSARIO STRAORDINARIO PER L'ATTUAZIONE DEGLI INTERVENTI PER LA MITIGAZIONE DEL RISCHIO IDROGEOLOGICO NELLA REGIONE PUGLIA
- Beneficiary
- COMMISSARIO STRAORDINARIO PER L'ATTUAZIONE DEGLI INTERVENTI PER LA MITIGAZIONE DEL RISCHIO IDROGEOLOGICO NELLA REGIONE PUGLIA
- Executor
-
RTI CAROSIELLI VITO
PLANETEK ITALIA SRL
LEXMEDIA SRL
ING. LOBEFARO ANGELO
ING. CARBONE FILOMENA
Programming area
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 2,770,000.00
- Payments on cohesion funds
- € 542,543.63
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico