CUP: E57D13000010001
18IR154/G1 - CONSOLIDAMENTO DEL VERSANTE NORD DEL SANTUARIO MADONNA DEL CASTELLO
SUMMARY OF THE PROJECT
SISTEMAZIONE IDROGEOLOGICA E CONSOLIDAMENTO DEL VERSANTE IN FRANA CON REALIZZAZIONE DI UN MURO DI CONTENIMENTO AL PIEDE E GRADONATURA IN GABBIONI SUL VERSANTE. RILOCAZIONE STRADA ACCESSO AL SANTUARIO.
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 90 num
- Achieved
- -
Download project
Funding monitored
€ 2,980,000.00
of which cohesion funds
€ 2,980,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 2980000.00 |
Payments monitored
€ 612,783.27
of which cohesion funds
€ 612,783.27
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 2103.04 | 2103.04 | 0 |
2021 | 0 | 2103.04 | 0 |
2022 | 0 | 2103.04 | 0 |
2023 | 106755.26 | 108858.30 | 3 |
2024 | 503924.97 | 612783.27 | 20 |
State of progress
Open
Expected start: 10/01/2024
Effective start: not available
Expected end: 10/12/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA TUTELA DEL TERRITORIO E DEL MARE-DIREZIONE GENERALE PER LA SALVAGUARDIA DEL TERRITORIO E DELLE ACQUE
- Implementing body
- COMMISSARIO STRAORDINARIO DELEGATO PER LA MITIGAZIONE DEL RISCHIO IDROGEOLOGICO IN CALABRIA
- Beneficiary
- COMMISSARIO STRAORDINARIO DELEGATO PER LA MITIGAZIONE DEL RISCHIO IDROGEOLOGICO IN CALABRIA
- Executor
- CONSORZIO STABILE GRANDI INFRASTRUTTURE ITALIANE SOCIETÃ CONSORTILE S.C.A.R.L.
Programming area
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 2,980,000.00
- Payments on cohesion funds
- € 612,783.27
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico