CUP: G32G20001190003
PROGETTO PER LA RIMOZIONE AMIANTO DELLA COPERTURA PALESTRA POLO SCOLASTICO IN VIA SAN GEMINIANO A GUIGLIA
SUMMARY OF THE PROJECT
IL PROGETTO PREVEDE LA RIMOZIONE E LO SMALTIMENTO DEL MANTO DI COPERTURA IN CEMENTO-AMIANTO. RIMOZIONE DELLE CONVERSE E COPERTURE LATERALI ALLA COPERTURA IN CEMENTO AMIANTO. RIMOZIONE IMPIANTO SOLARE TERMICO E FOTOVOLTAICO. INTERVENTO COMPRENSIVO DI AUTOGRù PER LA RIMOZIONE DEI MATERIALI, PIATTAFORMA PER LE LAVORAZIONI IN SICUREZZA, PONTEGGIO PER L¿ACCESSIBILITà ALLA COPERTURA E ACCANTIERAMENTO DELL¿AREA INTERESSATA
Implementation indicator
Superficie oggetto di intervento
- Target
- 850 mq
- Achieved
- 850 mq
Download project
Funding monitored
€ 42,643.80
of which cohesion funds
€ 42,643.80
Given name | Amount |
---|---|
Development and Cohesion Fund | 42643.80 |
Payments monitored
€ 31,620.22
of which cohesion funds
€ 31,620.22
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 31620.22 | 31620.22 | 74 |
State of progress
Open
Expected start: 20/03/2023
Effective start: 21/03/2023
Expected end: 20/05/2023
Effective end: 05/07/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI GUIGLIA
- Beneficiary
- REGIONE EMILIA-ROMAGNA
Programming area
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 42,643.80
- Payments on cohesion funds
- € 31,620.22
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Bonifiche
Other projects in territory
Same theme
RIQUALIFICAZIONE ENERGETICA DELLA SCUOLA ELEMENTARE E MEDIA | € 417,716 |
PROGETTAZIONE SICUREZZA 0360170798 VIA FOSSE ARDEATINE 42 41050 | € 80,000 |
Same type of investment