CUP: J59E20000510005
LAVORI DI SOSTITUZIONE DEL MANTO DI COPERTURA IN MATERIALE CEMENTIZIO CONTENENTE AMIANTO ALLA SCUOLA DELL¿INFANZIA PERTINI.
SUMMARY OF THE PROJECT
L¿INTERVENTO CONSISTE NELLA RIMOZIONE DELL¿ATTUALE MANTO DI COPERTURA DISPOSTO SU PIù FALDE COMPOSTO DA PANNELLI ONDULATI IN CEMENTOAMIANTO ¿ETERNIT¿ ED IL SUCCESSIVO RIFACIMENTO DELLA COPERTURA CON PANNELLI METALLICI COIBENTATI MANTENENDO LA CONFORMAZIONE ORIGINALE, QUINDI SENZA MODIFICHE DI PENDENZE O DELLE FALDE. L¿INTERVENTO RIGUARDA UNA SUPERFICIE DI CIRCA 624 MQ
Implementation indicator
Superficie oggetto di intervento
- Target
- 624.61 mq
- Achieved
- 0 mq
Download project
Funding monitored
€ 50,652.18
of which cohesion funds
€ 50,652.18
Given name | Amount |
---|---|
Development and Cohesion Fund | 50652.18 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 30/09/2022
Effective start: not available
Expected end: 15/09/2023
Effective end: not available
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI PISA
- Beneficiary
- REGIONE TOSCANA
Programming area
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,652.18
- Payments on cohesion funds
- € 0.00
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Bonifiche