CUP: E19B20000030002
LAVORI DI COMPLETAMENTO E RIFUNZIONALIZZAZIONE RETE FOGNARIA COMUNALE E DI COLLETTAMENTO - COMUNE CASTELLABATE
SUMMARY OF THE PROJECT
GLI INTERVENTI DEL PRESENTE PROGETTO HANNO L¿OBIETTIVO DI COMPLETARE E RIFUNZIONALIZZARE LA RETE FOGNARIA DEL COMUNE DI CASTELLABATE. QUESTI INTERVENTI SERVONO A OTTIMIZZARE IL FUNZIONAMENTO IDRAULICO DELLA RETE ED A RIDURRE I CONSUMI ED I COSTI ENERGETICI LEGATI AGLI IMPIANTI DI SOLLEVAMENTO. SI REALIZZANO OPERE CHE PERSEGUONO LE SEGUENTI FINALITà PRINCIPALI: A) COMPLETARE LA RETE FOGNARIA ESISTENTE; B) RIFUNZIONALIZZARE LA RETE FOGNARIA ESISTENTE; C) OTTIMIZZARE IL FUNZIONAMENTO IDRAULICO DELLA RETE FOGNARIA; D) DIMINUIRE I COSTI DI GESTIONE DELLA RETE FOGNARIA
Download project
Funding monitored
€ 7,450,000.00
of which cohesion funds
€ 6,650,000.00
Given name | Amount |
---|---|
Revolving Fund | 800000.00 |
Development and Cohesion Fund | 6650000.00 |
Payments monitored
€ 522,181.21
of which cohesion funds
€ 522,181.21
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 522181.21 | 522181.21 | 7 |
State of progress
Open
Expected start: 10/10/2023
Effective start: 10/10/2023
Expected end: 31/10/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA TUTELA DEL TERRITORIO E DEL MARE-DIREZIONE GENERALE PER LA SALVAGUARDIA DEL TERRITORIO E DELLE ACQUE
- Implementing body
- CONSAC GESTIONI IDRICHE SPA
- Beneficiary
- ENTE IDRICO CAMPANO
Programming area
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 6,650,000.00
- Payments on cohesion funds
- € 522,181.21
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche