CUP: G83E20000060002
MANUTENZIONE RETE IDRICA - COMUNE DI MIRABELLO SANNITICO
SUMMARY OF THE PROJECT
MIGLIORAMENTO DEL SISTEMA ACQUEDOTTISTICO DI DISTRIBUZIONE CON RIDUZIONE DEI VOLUMI DI ACQUA IMMESSI NELLE RETI DI DISTRIBUZIONE, AUMENTO DEI VOLUMI CONTABILIZZATI E REALIZZAZIONE DI INTERVENTI INFRASTRUTTURALI.
Implementation indicator
Popolazione addizionale servita dall'approvvigionamento idrico potenziato
- Target
- 200 num
- Achieved
- 0 num
Funding monitored
€ 261,817.50
of which cohesion funds
€ 216,367.50
Given name | Amount |
---|---|
Development and Cohesion Fund | 216367.50 |
Municipality | 45450.00 |
Payments monitored
€ 194,614.04
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 39346.24 | 39346.24 | 15 |
2024 | 155267.80 | 194614.04 | 74 |
State of progress
Open
Expected start: 01/04/2023
Effective start: 28/02/2023
Expected end: 31/07/2024
Effective end: not available
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA TUTELA DEL TERRITORIO E DEL MARE-DIREZIONE GENERALE PER LA SALVAGUARDIA DEL TERRITORIO E DELLE ACQUE
- Implementing body
- COMUNE DI MIRABELLO SANNITICO
- Beneficiary
- REGIONE MOLISE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche