CUP: I52G17000100005
LAVORI DI ADEGUAMENTO E COMPLETAMENTO DELLA RETE FOGNARIA COMUNALE - COMUNE: SAN GIORGIO LA MOLARA - AGGLOMERATO: SAN GIORGIO LA MOLARA
SUMMARY OF THE PROJECT
L INTERVENTO, PREVISTO E PROGRAMMATO PER IL TERRITORIO COMUNALE DI SAN GIORGIO LA MOLARA, SARà A SERVIZIO DELLA COLLETTIVITà E CONSISTE NELLA REALIZZAZIONE DI ALCUNI TRATTI DI RETE FOGNARIA A POTENZIAMENTO DELLA FOGNA ESISTENTE NELLA ZONA A NORD DEL CENTRO ABITATO ED DI ALCUNI TRATTI A SERVIZIO DI NUOVE AREE TERRITORIALI NELLE CONTRADE CUPITELLA, VIGNE VECCHIE, SAN NICOLA E MADDALENA. L INTERVENTO PREVISTO TIENE CONTO DELL INTERO FABBISOGNO DELLA ZONA, GARANTENDO IL SUPERAMENTO DELLE PROCEDURE DI INFRAZIONE N° 2014/2059 ART. 3. E 4.. LA COPERTURA DEL SISTEMA FOGNARIO-DEPURATIVO DALL ATTUALE 75 % PASSERà AL 95%.
Funding monitored
€ 2,996,428.26
of which cohesion funds
€ 2,996,428.26
Given name | Amount |
---|---|
Development and Cohesion Fund | 2996428.26 |
Payments monitored
€ 454,615.51
of which cohesion funds
€ 454,615.51
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 454615.51 | 454615.51 | 15 |
State of progress
Open
Expected start: 01/05/2021
Effective start: 10/07/2023
Expected end: 31/12/2022
Effective end: not available
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA TUTELA DEL TERRITORIO E DEL MARE-DIREZIONE GENERALE PER LA SALVAGUARDIA DEL TERRITORIO E DELLE ACQUE
- Implementing body
- COMUNE DI SAN GIORGIO LA MOLARA
- Beneficiary
- ENTE IDRICO CAMPANO
- Executor
- VELLA GROUP
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche