CUP: D26H17000560006
NUOVO PARCO DEPURATIVO Â LOTTO 4 Â VASCA DI PRIMA PIOGGIA IN LOC. MAINARDE
SUMMARY OF THE PROJECT
IL PROGETTO PREVEDE LA REALIZZAZIONE DI UNO SFIORO DI RETE FOGNARIA SU VIA DEL CIRCUITO PESCARA VERSO IL SOLLEVAMENTO LE MAINARDE E REALIZZAZIONE VASCHE DI PRIMA PIOGGIA DI 9.000 MC IN PROSSIMITÃ DEL SOLLEVAMENTO MAINARDE.
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 20,000 num
- Achieved
- 0 num
Download project
Funding monitored
€ 3,268,351.87
of which cohesion funds
€ 2,614,681.50
Given name | Amount |
---|---|
Revolving Fund | 653670.37 |
Development and Cohesion Fund | 2614681.50 |
Payments monitored
€ 123,354.91
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 45972.80 | 45972.80 | 1 |
2021 | 34597.25 | 80570.05 | 2 |
2022 | 40805.53 | 121375.58 | 3 |
2023 | 1979.33 | 123354.91 | 3 |
State of progress
Open
Expected start: 01/01/2023
Effective start: not available
Expected end: 31/10/2024
Effective end: not available
Entities
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche