CUP: H99E18000070006
RIFACIMENTO RETE ADDUZIONE INTERCOMUNALE VAL TIDONE - 1° STRALCIO LOC. BRENO SOSTITUZIONE TUBAZIONE CARICAMENTO RIO FRASSINETTI IN LOC. BRENO SOGGETTA A NUMEROSI GUASTI CHE COMPROMETTONO L'APPROVVIGIONAMENTO DI TUTTA L'ALTA VAL TIDONE.
SUMMARY OF THE PROJECT
Sostituzione tubazione caricamento Rio Frassinetti in loc. Breno soggetta a numerosi guasti che compromettono l'approvvigionamento di tutta l'Alta val Tidone.
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 30,000 num
- Achieved
- 30,000 num
Download project
Funding monitored
€ 811,993.77
of which cohesion funds
€ 270,000.00
Given name | Amount |
---|---|
Revolving Fund | 541993.77 |
Development and Cohesion Fund | 270000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 28/08/2020
Effective start: 31/05/2020
Expected end: 28/08/2020
Effective end: 09/05/2021
Entities
Programming area
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 270,000.00
- Payments on cohesion funds
- € 0.00
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche
Other projects in territory
Same theme
Same type of investment
Interventi di sistemazione idrogeologica nel comune di Ziano Piacentino (PC). | € 200,045 |