CUP: H53H18000070004
RINNOVO RETE IDRICA DI DISTRIBUZIONE E ALLACCIAMENTI_SANTA MARIA ROTONDA VIGNOLA VIA MONTORI-COLLINA-MONTORSI SOSTITUZIONE DI TRATTO DI CONDOTTA IDRICA E RELATIVI ALLACCIAMENTI AI FABBRICATI
SUMMARY OF THE PROJECT
Rinnovo rete idrica per circa 950 metri e allacciamenti nel Quartiere Santa Maria Rotonda (via Montori, via Collina, via Ori Zaira, via Nando Montorsi, via Collina, via Elio Monari)
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 1,000 num
- Achieved
- 1,000 num
Download project
Funding monitored
€ 260,000.00
of which cohesion funds
€ 90,000.00
Given name | Amount |
---|---|
Revolving Fund | 170000.00 |
Development and Cohesion Fund | 90000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 01/04/2022
Effective start: 03/01/2023
Expected end: 31/12/2022
Effective end: 06/06/2023
Entities
Programming area
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 90,000.00
- Payments on cohesion funds
- € 0.00
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche
Other projects in territory
Same theme
Interventi nel fiume Panaro e affluenti pedecollinari ai fini della messa in sicurezza territoriale | € 1,100,000 |
RINNOVO RETE IDRICA DI DISTRIBUZIONE E ALLACCIAMENTI-VIA DOCCIA VIGNOLA | € 160,500 |