CUP: J92G18000020007
RAZIONALIZZAZIONE SISTEMI DI COLLETTAMENTO E DEPURAZIONE NEI COMUNI DI ALICE BEL COLLE, RICALDONE, MONTALDO BORMIDA
SUMMARY OF THE PROJECT
L'INTERVENTO PREVEDE IL COLLETTAMENTO DELLO SCARICO DI ALICE BEL COLLE ALL'IMPIANTO DI ACQUI TERME E INTERVENTI DI OTTIMIZZAZIONE DEGLI IMPIANTI DI RICALDONE E MONTALDO BORMIDA
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 14,000 num
- Achieved
- -
Funding monitored
€ 2,000,000.00
of which cohesion funds
€ 1,000,000.00
Given name | Amount |
---|---|
Revolving Fund | 1000000.00 |
Development and Cohesion Fund | 1000000.00 |
Payments monitored
€ 1,312,630.24
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 5919.00 | 5919.00 | 0 |
2022 | 286254.92 | 292173.92 | 14 |
2023 | 1020456.32 | 1312630.24 | 65 |
State of progress
Open
Expected start: 14/03/2023
Effective start: 14/03/2023
Expected end: 13/09/2024
Effective end: not available
Entities
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche