CUP: E58F15000050001
REVAMPING E POTENZIAMENTO DELL¿IMPIANTO DI TRATTAMENTO MECCANICO E BIOLOGICO DEI RIFIUTI URBANI PER L¿INSERIMENTO DI UNA LINEA DI RECUPERO DI MATERIA ED ENERGIA - LOCALITà NOCE MATTEI SULMONA (AQ)
SUMMARY OF THE PROJECT
L'INTERVENTO PREVEDE DUE SUB INTERVENTI ALL'INTERNO DEL TMB TRATTAMENTO MECCANICO E BIOLOGICO IL PRIMO PREVEDE L'INSERIMENTO, NELL'ATTUALE REPARTO DI SELEZIONE MECCANICA, DI ATTREZZATURE ELETTROMECCANICHE PER IL RECUPERO DI CARTA E PLASTICA PRESENTI NEL RIFIUTO URBANO INDIFFERENZIATO, IL SECONDO PREVEDE L'ISTALLAZIONE DI UN NUOVO IMPIANTO PER LA PRODUZIONE DI COMBUSTIBILE SOLITO SECONDARIO CSS ATTRAVERSO IL TRATTAMENTO MECCANO-CHIMICO SIA NEL SOTTOVAGLIO CHE SULLA PARTE RESIDUALE A VALLE DEL RECUPERO DI MATERIA
Implementation indicator
Capacita' addizionale di riciclaggio dei rifiuti
- Target
- 8,000 ton/a
- Achieved
- 0 ton/a
Download project
Funding monitored
€ 3,372,256.10
of which cohesion funds
€ 2,500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 2500000.00 |
Another public source | 872256.10 |
Payments monitored
€ 1,441,001.11
of which cohesion funds
€ 1,441,001.11
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 20150.00 | 20150.00 | 0 |
2017 | 173744.00 | 193894.00 | 5 |
2018 | 584016.27 | 777910.27 | 23 |
2019 | 367938.10 | 1145848.37 | 33 |
2020 | 154452.74 | 1300301.11 | 38 |
2021 | 140700.00 | 1441001.11 | 42 |
State of progress
Open
Expected start: 27/02/2018
Effective start: 27/02/2018
Expected end: 30/11/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COGESA SPA
- Beneficiary
- REGIONE ABRUZZO
- Executor
- BELMONTE INVESTMENTS LIMITED
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rifiuti