CUP: D11B10000010006
ONDA VERDE
Download project
Funding monitored
€ 39,758.42
of which cohesion funds
€ 18,549.99
Given name | Amount |
---|---|
European Union | 7568.16 |
Revolving Fund (National co-financing) | 9147.42 |
Region | 2642.84 |
Municipality | 20400.00 |
- Economies:
- € 1,041.58
Payments monitored
€ 39,758.42
of which cohesion funds
€ 18,549.99
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2012 | 36370.42 | 36370.42 | 91 |
2013 | 3388.00 | 39758.42 | 100 |
State of progress
Completed
Expected start: 23/05/2011
Effective start: 23/05/2011
Expected end: 09/09/2014
Effective end: 09/09/2014
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Transport and mobility
- Promozione di trasporti urbani non inquinanti
Territory
Entities
- Planning body
- REGIONE MARCHE
- Implementing body
- COMUNE DI COLLI DEL TRONTO
- Beneficiary
- COMUNE DI COLLI DEL TRONTO
- Executor
-
SCHIAVI VALENTINA
ESSEGI SNC DI SCHIAVI GIANLUIGI & C.
DELTA SEGNALETICA SRL
- Priority QSN
- Reti e collegamenti per la mobilità
- General objective QSN
- Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
- Specific objective QSN
- Promuovere la mobilità urbana sostenibile e la logistica urbana
Programming area
- Programme
- ROP RCE ERDF MARCHE
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 18,549.99
- Payments on cohesion funds
- € 18,549.99
- Axis
- Accessibilità ai servizi di trasporto
- Operational objective
- Favorire l'offerta di un servizio di trasporto integrato.
Other projects in territory
Same theme
Realizzazione parcheggio di scambio in via Foscolo - Fermata ferroviaria | € 275,314 |
Same type of investment
FOTOVOLTAICO COLLI DEL TRONTO: SCUOLA PRIMARIA | € 141,119 |
COLLI DEL TRONTO: SCUOLA PRIMARIA VIA DEL PARTIGIANO | € 59,439 |