CUP: G83B11000420006
RISTRUTTURAZIONE DELL¿IMPIANTO TERMICO DELLA SCUOLA ELEMENTARE DON REMO TONOLI
Download project
Funding monitored
€ 275,719.79
of which cohesion funds
€ 275,719.79
Given name | Amount |
---|---|
European Union | 109295.32 |
Status: other measures | 165873.03 |
Region | 551.44 |
Payments monitored
€ 275,719.79
of which cohesion funds
€ 275,719.79
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 192753.97 | 192753.97 | 69 |
2015 | 85472.50 | 278226.47 | 100 |
2016 | -2506.68 | 275719.79 | 100 |
State of progress
Completed
Expected start: 24/09/2012
Effective start: 24/09/2012
Expected end: 22/12/2012
Effective end: 22/12/2012
Type
- Infrastructure
- RISTRUTTURAZIONE
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- REGIONE LOMBARDIA
- Implementing body
- COMUNE DI COCCAGLIO
- Beneficiary
- COMUNE DI COCCAGLIO
- Executor
- COMUNE DI COCCAGLIO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Diversificazione delle fonti energetiche e aumento dell'energia prodotta da fonti rinnovabili
Programming area
- Programme
- ROP RCE ERDF LOMBARDY
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 275,719.79
- Payments on cohesion funds
- € 275,719.79
- Axis
- Energia
- Operational objective
- Incremento della produzione energetica da fonti rinnovabili e sviluppo della cogenerazione.
Other projects in territory
Same theme
Same type of investment
RISTRUTTURAZIONE DELL¿IMPIANTO TERMICO DEL MUNICIPIO, TRAMITE L¿INTRODUZIONE DI UNA POMPA DI CALORE ARIA - ACQUA | € 163,059 |