CUP: F89D11000420002
Realizzazione di un parcheggio interrato in piazza C. Bilotti
Download project
Funding monitored
€ 2,119,472.43
of which cohesion funds
€ 2,119,472.43
Given name | Amount |
---|---|
Revolving Fund (Cohesion Action Plan) | 2119472.43 |
Payments monitored
€ 2,119,472.43
of which cohesion funds
€ 2,108,589.11
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 1358997.25 | 1358997.25 | 64 |
2017 | 506206.08 | 1865203.33 | 88 |
2018 | 204088.00 | 2069291.33 | 97 |
2019 | 50181.10 | 2119472.43 | 100 |
State of progress
Completed
Expected start: 18/12/2013
Effective start: 18/12/2013
Expected end: 11/06/2015
Effective end: 15/02/2018
Type
- Infrastructure
- NUOVA REALIZZAZIONE
Theme
- Social inclusion and health
- Progetti integrati per la rigenerazione urbana e rurale
Territory
Entities
- Planning body
- AMMINISTRAZIONE REGIONALE - REGIONE CALABRIA
- Implementing body
- COMUNE DI COSENZA
- Beneficiary
- COMUNE DI COSENZA
- Priority QSN
- Competitività e attrattività delle città e dei sistemi urbani
- General objective QSN
- Promuovere la competitività, l'innovazione e l'attrattività delle città e delle reti urbane attraverso la diffusione di servizi avanzati di qualità, il miglioramento della qualità della vita, e il collegamento con le reti materiali e immateriali
- Specific objective QSN
- Elevare la qualità della vita, attraverso il miglioramento delle condizioni ambientali e la lotta ai disagi derivanti dalla congestione e dalle situazioni di marginalità urbana, al contempo valorizzando il patrimonio di identità e rafforzando la relazione della cittadinanza con i luoghi
Programming area
- Programme
- PROGRAMMA PAC CALABRIA
- 2007-2013 Cohesion Action Plan
- 2007-2013 Cohesion Action Plan
- Cohesion funds
- € 2,119,472.43
- Payments on cohesion funds
- € 2,108,589.11
- Line
- Salvaguardia
- Action
- PISU