CUP: H84G22000030009
L1 - Sviluppo aerostazione passeggeri (nuovo terminal partenze, adeguamento antisismico aerostazione esistente con riconfigurazione a terminal arrivi, riqualifica curbside airside e landside)
SUMMARY OF THE PROJECT
L1 - Sviluppo aerostazione passeggeri (nuovo terminal partenze, adeguamento antisismico aerostazione esistente con riconfigurazione a terminal arrivi, riqualifica curbside airside e landside)
Download project
Funding monitored
€ 75,000,000.00
of which cohesion funds
€ 37,500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 37500000.00 |
Another public source | 37500000.00 |
Payments monitored
€ 4,111,076.89
of which cohesion funds
€ 2,055,538.37
5%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 142925.94 | 142925.94 | 0 |
2024 | 3968150.95 | 4111076.89 | 5 |
State of progress
Open
Expected start: 02/01/2025
Effective start: not available
Expected end: 31/12/2026
Effective end: not available
Entities
- Planning body
- REGIONE CALABRIA
- Implementing body
- SACAL - Societ? Aeroportuale Calabrese
- Beneficiary
- SACAL - Societ? Aeroportuale Calabrese
Programming area
- Programme
- PSC REGIONE CALABRIA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 37,500,000.00
- Payments on cohesion funds
- € 2,055,538.37
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto aereo