Updated on 28/02/2025
Funding monitored € 180,000.00 of which cohesion funds € 110,000.00
Given name Amount
Another public source180000.00
Payments monitored € 159,224.04 of which cohesion funds € 97,303.58
Year Amount Cumulative amount Percentage on public financing
2019159224.04159224.0488

State of progress

Open
Expected start: 10/01/2018
Effective start: 10/01/2018
Expected end: 31/03/2018
Effective end: 31/03/2018

Entities

Planning body
REGIONE CALABRIA
Implementing body
COMUNE DI MONTALTO UFFUGO
Beneficiary
COMUNE DI MONTALTO UFFUGO

Programming area

Programme
POC CALABRIA
None
Piano d'Azione Coesione 2014/2020
Cohesion funds
€ 110,000.00
Payments on cohesion funds
€ 97,303.58
CAP area axis
Tutela e valorizzazione del patrimonio ambientale e culturale
CAP action line
Miglioramento delle condizioni e degli standard di offerta e fruizione del patrimonio culturale, nelle aree di attrazione