CUP: F17B18000400002
1.5 Le azioni comuni. 1.5.2 Riqualificazione e rifunzionalizzazione del complesso scuola S. Francesco
SUMMARY OF THE PROJECT
Riqualificazione e rifunzionalizzazione del complesso scuola S. Francesco
Implementation indicator
Superficie oggetto di intervento
- Target
- 1 mq
- Achieved
- 0 mq
Download project
Funding monitored
€ 2,000,000.00
of which cohesion funds
€ 2,000,000.00
Given name | Amount |
---|---|
Another public source | 2000000.00 |
Payments monitored
€ 1,910,389.38
of which cohesion funds
€ 1,910,389.38
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 35165.72 | 35165.72 | 1 |
2020 | 600.00 | 35765.72 | 1 |
2021 | 36814.76 | 72580.48 | 3 |
2022 | 914300.98 | 986881.46 | 49 |
2023 | 791539.73 | 1778421.19 | 88 |
2024 | 131968.19 | 1910389.38 | 95 |
State of progress
Completed
Expected start: 30/06/2019
Effective start: 29/12/2023
Expected end: 29/12/2023
Effective end: 29/12/2023
Entities
- Planning body
- REGIONE CALABRIA
- Implementing body
- COMUNE DI CROTONE
- Beneficiary
- COMUNE DI CROTONE
Programming area
- Programme
- POC CALABRIA
- None
- Piano d'Azione Coesione 2014/2020
- Cohesion funds
- € 2,000,000.00
- Payments on cohesion funds
- € 1,910,389.38
- CAP area axis
- Tutela e valorizzazione del patrimonio ambientale e culturale
- CAP action line
- Miglioramento delle condizioni e degli standard di offerta e fruizione del patrimonio culturale, nelle aree di attrazione