CUP: J33B12000230001
INTERVENTO INTEGRATO PER IL COMPLETAMENTO DELLE OPERE DI DIFESA COSTIERA E RICOSTRUZIONE DEL LITORALE (COPANELLO ¿ PUNTA STILO) - ECI05
SUMMARY OF THE PROJECT
INTERVENTO INTEGRATO PER IL COMPLETAMENTO DELLE OPERE DI DIFESA COSTIERA E RICOSTRUZIONE DEL LITORALE (COPANELLO ¿ PUNTA STILO) - ECI05
Implementation indicator
Lunghezza delle coste soggette a interventi di mitigazione del rischio di erosione costiera
- Target
- 1 km
- Achieved
- 0 km
Funding monitored
€ 2,248,000.00
of which cohesion funds
€ 2,248,000.00
Given name | Amount |
---|---|
European Union | 1686000.00 |
Revolving Fund | 178041.60 |
Region | 383958.40 |
Payments monitored
€ 1,816,578.09
of which cohesion funds
€ 1,816,578.09
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 4636.00 | 4636.00 | 0 |
2018 | 0 | 4636.00 | 0 |
2019 | 0 | 4636.00 | 0 |
2020 | 0 | 4636.00 | 0 |
2021 | 351635.32 | 356271.32 | 15 |
2022 | 911966.64 | 1268237.96 | 56 |
2023 | 548340.13 | 1816578.09 | 80 |
State of progress
Open
Expected start: 30/10/2019
Effective start: not available
Expected end: 30/10/2020
Effective end: not available
Entities
- Planning body
- REGIONE CALABRIA
- Implementing body
- REGIONE CALABRIA
- Beneficiary
- REGIONE CALABRIA
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF ESF CALABRIA
- Axis
- PREVENZIONE DEI RISCHI
- Specific objective
- Riduzione del rischio idrogeologico e di erosione costiera