CUP: I36G17000140004
POTENZIAMENTO DEL SERVIZIO DI RACCOLTA DIFFERENZIATA - Comune di Cetraro
SUMMARY OF THE PROJECT
POTENZIAMENTO DEL SERVIZIO DI RACCOLTA DIFFERENZIATA - Comune di Cetraro
Implementation indicator
Capacita' degli impianti o sistemi di raccolta oggetto di intervento
- Target
- 1,450 ton/a
- Achieved
- 526.43 ton/a
Download project
Funding monitored
€ 1,091,231.52
of which cohesion funds
€ 1,091,231.52
Given name | Amount |
---|---|
European Union | 246870.00 |
Revolving Fund | 82290.00 |
Municipality | 762071.52 |
Payments monitored
€ 735,893.28
of which cohesion funds
€ 735,893.28
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 506900.31 | 506900.31 | 46 |
2019 | 228992.97 | 735893.28 | 67 |
State of progress
Open
Expected start: 01/03/2018
Effective start: 05/03/2018
Expected end: 31/12/2021
Effective end: not available
Entities
- Planning body
- REGIONE CALABRIA
- Implementing body
- COMUNE DI CETRARO
- Beneficiary
- COMUNE DI CETRARO
Programming area
- Programme
- ROP ERDF ESF CALABRIA
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 1,091,231.52
- Payments on cohesion funds
- € 735,893.28
- Axis
- TUTELA E VALORIZZAZIONE DEL PATRIMONIO AMBIENTALE E CULTURAL
- Specific objective
- Ottimizzazione della gestione dei rifiuti urbani secondo la gerarchia comunitaria
At the School of OpenCohesion
OpenCoesione goes to School followed this project in edition 2020-21 with the team “Immaginiamo Il Domani IID” of “ISTITUTO COMPRENSIVO CETRARO” of Cetraro, COSENZA.
Read the Monithon report.
View the creative output.
Read the Monithon report.
View the creative output.