CUP: C33H04000000005
LAVORI DI COMPLETAMENTO DELLO SCHEMA IDRICO SULLA DIGA DEL TORRENTE MENTA. OPERE A VALLE DELLA CENTRALE IDROELETTRICA. IMPIANTO DI POTABILIZZAZIONE (DELIBERA DI GIUNTA REGIONALE N. 222 DEL 21.7.2015)
SUMMARY OF THE PROJECT
LAVORI DI COMPLETAMENTO DELLO SCHEMA IDRICO SULLA DIGA DEL TORRENTE MENTA. OPERE A VALLE DELLA CENTRALE IDROELETTRICA. IMPIANTO DI POTABILIZZAZIONE.
Implementation indicator
Capacità dell'impianto oggetto di intervento
- Target
- 10,000 mc
- Achieved
- 10,000 mc
Download project
Funding monitored
€ 15,388,265.13
of which cohesion funds
€ 15,388,265.13
Given name | Amount |
---|---|
Development and Cohesion Fund | 15388265.13 |
- Other resources - Private:
- € 685,229
Payments monitored
€ 14,067,828.86
of which cohesion funds
€ 14,067,828.86
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 2688883.98 | 2688883.98 | 17 |
2009 | 3694373.72 | 6383257.70 | 41 |
2010 | 2509531.34 | 8892789.04 | 57 |
2011 | 287220.00 | 9180009.04 | 59 |
2012 | 18128.06 | 9198137.10 | 59 |
2013 | 0 | 9198137.10 | 59 |
2014 | 287220.00 | 9485357.10 | 61 |
2015 | 423478.36 | 9908835.46 | 64 |
2016 | 399156.74 | 10307992.20 | 66 |
2017 | 2022155.24 | 12330147.44 | 80 |
2018 | 1379209.53 | 13709356.97 | 89 |
2019 | 358471.89 | 14067828.86 | 91 |
State of progress
Open
Expected start: 08/06/2016
Effective start: 08/06/2016
Expected end: 22/02/2019
Effective end: 22/02/2019
Entities
- Planning body
- REGIONE CALABRIA
- Implementing body
- SOCIETA RISORSE IDRICHE CALABRESI
- Beneficiary
- SOCIETA RISORSE IDRICHE CALABRESI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE CALABRIA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche