CUP: H56D12000060004
ATO 1 CS - ADEGUAMENTO DEGLI IMPIANTI DI DEPURAZIONE E REALIZZAZIONE OPERE DI COLLETTAMENTO NELL'AGGLOMERATO DI SANTA MARIA DEL CEDRO
SUMMARY OF THE PROJECT
ATO 1 CS - ADEGUAMENTO DEGLI IMPIANTI DI DEPURAZIONE E REALIZZAZIONE OPERE DI COLLETTAMENTO NELL'AGGLOMERATO DI SANTA MARIA DEL CEDRO
Implementation indicator
Estensione della rete
- Target
- 143 km
- Achieved
- 0 km
Download project
Funding monitored
€ 7,000,000.00
of which cohesion funds
€ 7,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 7000000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 31/05/2016
Effective start: not available
Expected end: 31/12/2017
Effective end: not available
Entities
- Planning body
- REGIONE CALABRIA
- Implementing body
- COMUNE DI SANT'EUFEMIA D'ASPROMONTE
- Beneficiary
- COMUNE DI SANT'EUFEMIA D'ASPROMONTE
Programming area
- Programme
- PSC REGIONE CALABRIA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 7,000,000.00
- Payments on cohesion funds
- € 0.00
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche