CUP: H84E10000100006
REALIZZAZIONE IMPIANTO FOTOVOLTAICO SCUOLA PRIMARIA VIA BERLINGUER
Download project
Funding monitored
€ 79,174.97
of which cohesion funds
€ 109,055.00
Given name | Amount |
---|---|
European Union | 44535.92 |
Revolving Fund (National co-financing) | 7422.66 |
Region | 7422.65 |
Another public source | 19793.74 |
- Economies:
- € 29,880.03
Payments monitored
€ 79,174.97
of which cohesion funds
€ 79,174.97
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2012 | 43655.43 | 43655.43 | 55 |
2013 | 30949.00 | 74604.43 | 94 |
2014 | 0 | 74604.43 | 94 |
2015 | 4570.54 | 79174.97 | 100 |
State of progress
Completed
Expected start: 12/03/2012
Effective start: 12/03/2012
Expected end: 12/05/2012
Effective end: 12/05/2012
Entities
- Planning body
- REGIONE CALABRIA
- Implementing body
- COMUNE DI PETILIA POLICASTRO
- Beneficiary
- COMUNE DI PETILIA POLICASTRO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Diversificazione delle fonti energetiche e aumento dell'energia prodotta da fonti rinnovabili
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP CONV ERDF CALABRIA
- Axis
- Asse II - Energia
- Operational objective
- Diversificare le fonti energetiche e aumentare l'energia prodotta da fonti rinnovabili.