Lavori di adeguam. potenz. e risanam. ambientale del sitema fognario comunale
Download project
Funding monitored
€ 2,941,818.08
of which cohesion funds
€ 2,237,800.80
Given name | Amount |
---|---|
European Union | 1678350.60 |
Revolving Fund (National co-financing) | 310203.95 |
Region | 249246.25 |
Payments monitored
€ 2,902,074.40
of which cohesion funds
€ 2,237,800.80
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 2385158.32 | 2385158.32 | 81 |
2016 | 3050.00 | 2388208.32 | 81 |
2017 | 382190.68 | 2770399.00 | 94 |
2018 | 121286.53 | 2891685.53 | 98 |
2019 | 10388.87 | 2902074.40 | 98 |
State of progress
Completed
Expected start: 16/06/2015
Effective start: 16/06/2015
Expected end: 13/10/2015
Effective end: 12/04/2016
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Environment
- Trattamento delle acque (potabili)
Territory
Entities
- Planning body
- REGIONE CAMPANIA
- Implementing body
- COMUNE DI SERINO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- Programme
- ROP CONV ERDF CAMPANIA
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 2,237,800.80
- Payments on cohesion funds
- € 2,237,800.80
- Axis
- Sostenibilità ambient. e attrattività culturale e turistica
- Operational objective
- MIGLIORARE LA GESTIONE INTEGRATA DELLE RISORSE IDRICHE.