CUP: I39G13001060002
COMPLET IMPIANTO FOGNARIO E RAZIONALIZ IMPIANTI DEPURAZ 1° STRALCIO FUNZIONALE
Download project
Funding monitored
€ 3,213,604.41
of which cohesion funds
€ 1,794,330.50
Given name | Amount |
---|---|
European Union | 1345747.88 |
Revolving Fund (National co-financing) | 248730.09 |
Region | 199852.53 |
Payments monitored
€ 2,987,379.22
of which cohesion funds
€ 1,794,330.50
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 1817529.24 | 1817529.24 | 56 |
2016 | 0 | 1817529.24 | 56 |
2017 | 1166649.98 | 2984179.22 | 92 |
2018 | 3200.00 | 2987379.22 | 92 |
State of progress
Open
Expected start: 30/03/2015
Effective start: 30/03/2015
Expected end: 31/12/2015
Effective end: 16/02/2017
Type
- Infrastructure
- AMPLIAMENTO O POTENZIAMENTO
Theme
- Environment
- Trattamento delle acque (potabili)
Territory
Entities
- Planning body
- REGIONE CAMPANIA
- Implementing body
- COMUNE DI FELITTO
- Beneficiary
- COMUNE DI FELITTO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, qualità e efficienza del servizio di gestione dei rifiuti, rafforzando le filiere produttive a esso collegate e recuperare alle opportunità di sviluppo sostenibile i siti contaminati, anche a tutela della salute pubblica
Programming area
- Programme
- ROP CONV ERDF CAMPANIA
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 1,794,330.50
- Payments on cohesion funds
- € 1,794,330.50
- Axis
- Sostenibilità ambient. e attrattività culturale e turistica
- Operational objective
- MIGLIORARE LA GESTIONE INTEGRATA DELLE RISORSE IDRICHE.