CUP: H89G13000660006
Realizz. rete fognarie loc. Caselle-Utracchi e Casale-Campomarino e imp. dep Pon
Download project
Funding monitored
€ 795,261.33
of which cohesion funds
€ 614,795.99
Given name | Amount |
---|---|
European Union | 461096.99 |
Revolving Fund (National co-financing) | 85223.02 |
Region | 68475.98 |
Payments monitored
€ 779,952.85
of which cohesion funds
€ 614,795.99
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 614878.40 | 614878.40 | 77 |
2016 | 2622.00 | 617500.40 | 77 |
2017 | 105844.57 | 723344.97 | 90 |
2018 | 22775.16 | 746120.13 | 93 |
2019 | 33832.72 | 779952.85 | 98 |
State of progress
Completed
Expected start: 14/07/2016
Effective start: 14/07/2016
Expected end: 14/07/2016
Effective end: 14/07/2016
Type
- Infrastructure
- NUOVA REALIZZAZIONE
Theme
- Environment
- Gestione e distribuzione d'acqua (potabile)
Territory
Entities
- Planning body
- REGIONE CAMPANIA
- Implementing body
- COMUNE DI OSPEDALETTO D''ALPINOLO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- Programme
- ROP CONV ERDF CAMPANIA
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 614,795.99
- Payments on cohesion funds
- € 614,795.99
- Axis
- Sostenibilità ambient. e attrattività culturale e turistica
- Operational objective
- MIGLIORARE LA GESTIONE INTEGRATA DELLE RISORSE IDRICHE.