CUP: F81E07000000004
Rinaturalizzazione del fosso collettore in località Sentina
SUMMARY OF THE PROJECT
Rinaturalizzazione del fosso collettore in località Sentina
Implementation indicator
Estensione della rete
- Target
- 0.60 km
- Achieved
- 0.60 km
Download project
Funding monitored
€ 195,289.31
of which cohesion funds
€ 44,806.07
Given name | Amount |
---|---|
Development and Cohesion Fund | 44806.07 |
Municipality | 150483.24 |
Payments monitored
€ 44,806.07
of which cohesion funds
€ 44,806.07
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 44806.07 | 44806.07 | 22 |
State of progress
Open
Expected start: 09/02/2009
Effective start: 09/02/2009
Expected end: 09/05/2009
Effective end: 09/05/2009
Entities
- Planning body
- REGIONE MARCHE
- Implementing body
- COMUNE DI SAN BENEDETTO DEL TRONTO
- Beneficiary
- COMUNE DI SAN BENEDETTO DEL TRONTO
- Executor
-
TREND PROJECT
TAFFONI STEFANO
SCHIAVI LUIGI & GIUSEPPE
RANCIAFFI ALESSANDRO
PULCINI CINZIA
NUOVE PROSPETTIVE
METAL WOOD
LATTANZI EMIDIO & FIGLIO
LA.MI.CIO.SCAVI
GRU SERVICE DI ASCOLANI G. & C.
Visualizzati i primi 10 soggetti di 21
Programming area
- Programme
- PSC REGIONE MARCHE
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 44,806.07
- Payments on cohesion funds
- € 44,806.07
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Natura e biodiversita'