CUP: E71B17000620006
(15892.31102017.120000012) PISTA CICLABILE VIA DEI TIGLI
SUMMARY OF THE PROJECT
IL TRATTO DA REALIZZARE INIZIA DALLA PISTA CICLABILE DI VIA DEI TIGLI E SI COLLEGA ALLA PISTA CICLABILE DI VIA DEL LAGO, IN PROSSIMIT? DI VIA NUOVA SI IMMETTE NELL?AREA VERDE PER CONSENTIRE L?ACCESSO ALL?UNIVERSIT?;CONSIDERATO CHE TALE INTERVENTO PERMETTER? DI INTEGRARE IL SISTEMA CICLOPEDONALE DI MOBILIT? DOLCE CON IL TRASPORTO PUBBLICO NELL?AMBITO DEL SISTEMA DI MOBILIT? COMPLESSIVO PROPRIO GRAZIE AL COLLEGAMENTO CON LA STAZIONE FERROVIARIA.
Implementation indicators
Diminuzione annuale stimata dei gas a effetto serra
- Target
- 1.50 teq
- Achieved
- 1.50 teq
Estensione in lunghezza (piste ciclabili)
- Target
- 0.64 km
- Achieved
- 0.64 km
Riduzione delle emissioni di PM10 tonnellate anno
- Target
- 6 ton/a
- Achieved
- 0 ton/a
Riduzione delle emissioni di Nox tonnellate anno
- Target
- 1.83 ton/a
- Achieved
- 0.07 ton/a
- Slide 1
- Slide 2
- Slide 3
- Slide 4
Download project
Funding monitored
€ 138,612.11
of which cohesion funds
€ 138,612.11
Given name | Amount |
---|---|
European Union | 53734.77 |
Revolving Fund | 37614.34 |
Region | 16120.43 |
Another public source | 31142.57 |
- Economies:
- € 17,100.75
Payments monitored
€ 138,612.11
of which cohesion funds
€ 130,755.39
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 9706.32 | 9706.32 | 7 |
2019 | 0 | 9706.32 | 7 |
2020 | 108300.00 | 118006.32 | 85 |
2021 | 20605.79 | 138612.11 | 100 |
State of progress
Completed
Expected start: 24/02/2020
Effective start: 10/02/2020
Expected end: 22/07/2020
Effective end: 20/01/2021
Entities
- Planning body
- REGIONE TOSCANA
- Beneficiary
- COMUNE DI CALENZANO
- Executor
- BONAIUTI MARCO
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF TUSCANY
- Axis
- SOSTENERE LA TRANSIZIONE VERSO UN'ECONOMIA A BASSA EMISSIONE
- Specific objective
- Aumento della mobilità sostenibile nelle aree urbane