CUP: F69J21003350002
PROGETTO TREVIGNANO SPIAGGE SICURE
SUMMARY OF THE PROJECT
STACCIONATE,CARTELLONISTICA,SERV. IGIENICI,PULIZIA SPIAGGE,NAVETTA WEEK END
Implementation indicator
Progetti per la fruizione integrata e la promozione
- Target
- 1 num
- Achieved
- 0 num
Download project
Funding monitored
€ 56,907.33
of which cohesion funds
€ 56,907.33
Given name | Amount |
---|---|
Development and Cohesion Fund | 56907.33 |
Payments monitored
€ 51,889.61
of which cohesion funds
€ 51,889.61
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 51889.61 | 51889.61 | 91 |
State of progress
Open
Expected start: 01/06/2021
Effective start: 01/06/2021
Expected end: 30/09/2021
Effective end: not available
Type
Theme
Territory
Entities
- Planning body
- REGIONE LAZIO
- Beneficiary
- COMUNE DI TREVIGNANO ROMANO
- Executor
-
SEBACH SPA
SCHIAFFINI TRAVEL SPA
L'OASI SOC. COOP.
CONSOL SOC. COOP.
Programming area
- Programme
- PSC LAZIO
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 56,907.33
- Payments on cohesion funds
- € 51,889.61
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Turismo e ospitalita'
Other projects in territory
Same theme
'Trevignano: viaggio nel passato con gli occhi del futuro' | € 106,646 |