CUP: G36J17000630002
EFFICIENTAMENTO ENERGETICO CASA PER ANZIANI "ADA E ALFREDO ARCICASA"
SUMMARY OF THE PROJECT
REALIZZAZIONE DI CAPPOTTO TERMICO E SOSTITUZIONE DELL'IMPIANTO DI ILLUMINAZIONE
Implementation indicators
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 139,666.23 KWh/a
- Achieved
- 109,149.46 KWh/a
Potenza installata
- Target
- 326 KW
- Achieved
- 135 KW
Superficie oggetto di intervento
- Target
- 2,132.96 mq
- Achieved
- 2,132.96 mq
- Slide 1
- Slide 2
- Slide 3
Download project
Funding monitored
€ 372,645.90
of which cohesion funds
€ 372,645.90
Given name | Amount |
---|---|
European Union | 186323.15 |
Revolving Fund | 130425.80 |
Region | 55896.95 |
- Other resources - Private:
- € 31,833
Payments monitored
€ 357,428.82
of which cohesion funds
€ 357,428.82
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 961.78 | 961.78 | 0 |
2019 | 21136.07 | 22097.85 | 5 |
2020 | 128323.68 | 150421.53 | 40 |
2021 | 199258.91 | 349680.44 | 93 |
2022 | 7748.38 | 357428.82 | 95 |
State of progress
Completed
Expected start: 16/11/2018
Effective start: 14/07/2020
Expected end: 15/05/2019
Effective end: 31/05/2021
Entities
Programming area
- Programme
- ROP ERDF FRIULI VENEZIA-GIULIA
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 372,645.90
- Payments on cohesion funds
- € 357,428.82
- Axis
- SOSTENERE LA TRANSIZIONE VERSO UN'ECONOMIA A BASSE EMISSIONI
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili