CUP: E11C18000080003
K13 - INTERVENTI FSC PER SICUREZZA RETI INTERCONNESSE RETE FERROVIENORD RAMO MILANO
SUMMARY OF THE PROJECT
O COMPLETAMENTO ATTREZZAGGIO SCMT SULLA RETE FERROVIENORD ¿ RAMO MILANO (COMO LAGO ¿ COMO - CAMERLATA) O INSTALLAZIONE DI UN SISTEMA DI RILEVAMENTO TEMPERATURE BOCCOLE PRESSO L¿IMPIANTO DI NOVATE MILANESE E L¿IMPIANTO DI BOVISIO MASCIAGO O SOSTITUZIONE APPARATO DI SICUREZZA ESISTENTE DELL¿IMPIANTO DI SEVESO COL SISTEMA ACC-M (APPARATO CENTRALE COMPUTERIZZATO MULTISTAZIONE) ¿ TRATTA CESANO M. ¿ SEVESO ¿ MEDA/CAMNAGO
Implementation indicator
Realizzazione di applicativi e sistemi informativi
- Target
- 4 num
- Achieved
- 0 num
Funding monitored
€ 7,323,636.46
of which cohesion funds
€ 5,628,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 5628000.00 |
Another public source | 1695636.46 |
Payments monitored
€ 4,827,911.62
of which cohesion funds
€ 3,791,695.03
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 2643567.65 | 2643567.65 | 36 |
2021 | 1521519.53 | 4165087.18 | 56 |
2022 | 662824.44 | 4827911.62 | 65 |
State of progress
Open
Expected start: 30/11/2018
Effective start: 13/12/2019
Expected end: 31/12/2023
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- FERROVIENORD SOCIETA PER AZIONI
- Beneficiary
- REGIONE LOMBARDIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana