CUP: E80D17000030003
ACQUISTO TRENI PER IL SERVIZIO FERROVIARIO LOMBARDO
SUMMARY OF THE PROJECT
VENGONO FINANZIATI 9 TRENI DIESEL NELL'AMBITO DEL PIANO DI RINNOVO DELLA FLOTTA FERROVIARIA LOMBARDA (DGR 6932/2017)
Implementation indicator
Unita' beni acquistati
- Target
- 9 num
- Achieved
- 8 num
Funding monitored
€ 57,555,000.00
of which cohesion funds
€ 29,136,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 29136000.00 |
Region | 28419000.00 |
Payments monitored
€ 25,428,419.05
of which cohesion funds
€ 12,872,598.69
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 5726722.50 | 5726722.50 | 9 |
2020 | 0 | 5726722.50 | 9 |
2021 | 0 | 5726722.50 | 9 |
2022 | 12967857.50 | 18694580.00 | 32 |
2023 | 6733839.05 | 25428419.05 | 44 |
State of progress
Open
Expected start: 01/12/2018
Effective start: 22/11/2018
Expected end: 31/12/2023
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- FERROVIENORD SOCIETA PER AZIONI
- Beneficiary
- REGIONE LOMBARDIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana
Other projects in territory
Same theme
RADDOPPIO CODOGNO - MANTOVA | € 831,877,735 |
SS. N.340 "REGINA" VARIANTE ALLA TREMEZZINA | € 576,074,955 |
PROLUNGAMENTO LINEA 5 DELLA METROPOLITANA DA GARIBALDI A SAN SIRO | € 385,000,000 |
ACQUISTO 26 TRENI PER IL SERVIZIO FERROVIARIO REGIONALE | € 222,700,000 |
ACQUISIZIONE DI MATERIALE ROTABILE PER IL SERVIZIO FERROVIARIO RL - TSR | € 217,040,000 |