CUP: D54J08000020001
¿RETTIFICA DEL MOLO SAN CATALDO E CALATA 1¿
SUMMARY OF THE PROJECT
RECUPERO STRUTTURALE DELLA BANCHINA DELLA CALATA 1 E DELL'AMPLIAMENTO DEL MOLO SAN CATALDO LATO LEVANTE
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 500 num
- Achieved
- 500 num
Funding monitored
€ 13,810,000.00
of which cohesion funds
€ 13,810,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 13810000.00 |
Payments monitored
€ 13,810,000.00
of which cohesion funds
€ 13,810,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 2777515.09 | 2777515.09 | 20 |
2020 | 2856757.54 | 5634272.63 | 40 |
2021 | 8175727.37 | 13810000.00 | 100 |
State of progress
Completed
Expected start: 17/10/2019
Effective start: 17/10/2019
Expected end: 31/12/2020
Effective end: 20/10/2021
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- AUTORITA DI SISTEMA PORTUALE DEL MAR IONIO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto marittimo