CUP: D71B17002010001
SRT 71 - VARIANTE ALLA SRT 71 IN COMUNE DI CORTONA
SUMMARY OF THE PROJECT
SRT 71 - REALIZZAZIONE DELLA VARIANTE ALLA SRT 71 DA SUD DELL'ABITATO DI CAMUCIA ALLO SVINCOLO CON LA PERUGIA-BETTOLLE NEL COMUNE DI CORTONA (AR)
Implementation indicator
Lunghezza totale delle strade di nuova costruzione
- Target
- 5 km
- Achieved
- 0 km
Funding monitored
€ 17,338,816.98
of which cohesion funds
€ 14,838,816.98
Given name | Amount |
---|---|
Development and Cohesion Fund | 15158214.95 |
Region | 2180602.03 |
Payments monitored
€ 6,769,464.44
of which cohesion funds
€ 5,555,484.96
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 3309.10 | 3309.10 | 0 |
2021 | 1045929.85 | 1049238.95 | 6 |
2022 | 372981.75 | 1422220.70 | 8 |
2023 | 5347243.74 | 6769464.44 | 39 |
State of progress
Open
Expected start: 01/10/2022
Effective start: 01/10/2022
Expected end: 10/10/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- REGIONE TOSCANA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale