CUP: F11B05000490001
SS.N.291 DELLA NURRA: LAVORI DI COSTRUZIONE DEL 1° LOTTO DA ALGHERO AD OLMEDO, IN LOCALITA BIVIO CANTONIERA DI RUDAS
SUMMARY OF THE PROJECT
L¿INTERVENTO Ê RELATIVO AL COMPLETAMENTO DEL COLLEGAMENTO TRA LE CITTà DI SASSARI ED ALGHERO MEDIANTE UNA STRADA EXTRAURBANA PRINCIPALE DI CAT. B DEL DM 5/11/2001, GIà REALIZZATA FINO ALLA LOCALITà OLMEDO. IL PRIMO LOTTO, OGGETTO DEL PRESENTE INTERVENTO, COMPLETA L¿ITINERARIO FINO AD ALGHERO E HA UNA ESTENSIONE DI CIRCA 4,1 KM SULL¿ASSE PRINCIPALE E 3,2 KM SULLA BRETELLA DI CIRCONVALLAZIONE DELL¿ABITATO DI ALGHERO. L¿INTERVENTO COMPRENDE ANCHE LA CONNESSIONE TRA L¿ASSE PRINCIPALE IN CORRISPONDENZA DELLO SVINCOLO DI MAMUNTANAS E L¿AEROPORTO DI ALGHERO CON SEZIONE TIPO C DI LUNGHEZZA CIRCA 3,2 KM (4° LOTTO).
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 10.50 km
- Achieved
- 0 km
Funding monitored
€ 238,067,052.70
of which cohesion funds
€ 25,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 25000000.00 |
Another public source | 213067052.70 |
Payments monitored
€ 1,690,493.10
of which cohesion funds
€ 1,118.70
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 77872.01 | 77872.01 | 0 |
2016 | 202732.19 | 280604.20 | 0 |
2017 | 115968.39 | 396572.59 | 0 |
2018 | 237325.90 | 633898.49 | 0 |
2019 | 57992.72 | 691891.21 | 0 |
2020 | 31659.40 | 723550.61 | 0 |
2021 | 467420.48 | 1190971.09 | 0 |
2022 | 489114.08 | 1680085.17 | 0 |
2023 | 10407.93 | 1690493.10 | 0 |
State of progress
Open
Expected start: 01/05/2024
Effective start: not available
Expected end: 31/10/2027
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale