CUP: F81B19000330001
LAVORI DI EFFICIENTAMENTO ENERGETICO SCUOLA PRIMARIA E D'INFANZIA
SUMMARY OF THE PROJECT
INTERVENTI DI EFFICIENTAMENTO ENERGETICO DEL FABBRICATO CHE OSPITA LA SCUOLA, IN PARTICOLARE L¿INSTALLAZIONE DI UN IMPIANTO FOTOVOLTAICO SULLA COPERTURA DEL FABBRICATO E IL RIPRISTINO DELLA FUNZIONALITà DELL¿IMPIANTO SOLARE-TERMICO A SERVIZIO DEL CAMPEGGIO E DELLA SCUOLA DI INFANZIA
Implementation indicator
Numero edifici scolastici oggetto dell'intervento
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 48,190.00
of which cohesion funds
€ 48,190.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 48190.00 |
Payments monitored
€ 48,190.00
of which cohesion funds
€ 48,190.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 9638.00 | 9638.00 | 20 |
2020 | 33733.00 | 43371.00 | 90 |
2021 | 4819.00 | 48190.00 | 100 |
State of progress
Completed
Expected start: 20/08/2019
Effective start: 20/08/2019
Expected end: 31/03/2020
Effective end: 30/06/2020
Entities
- Planning body
- COMUNE DI ARVIER
- Beneficiary
- COMUNE DI ARVIER
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile