Updated on 20/07/2021
Funding monitored € 8,000,000.00 of which cohesion funds € 8,000,000.00
Given name Amount
Revolving Fund (Cohesion Action Plan)8000000.00
Payments monitored € 9,836,667.58 of which cohesion funds € 8,005,910.05
Year Amount Cumulative amount Percentage on public financing
2015471985.07471985.075
2016747944.901219929.9715
20171871533.373091463.3438
20181837829.554929292.8961
20193530335.638459628.52105
20201347960.069807588.58122
202129079.009836667.58122

State of progress

Completed
Expected start: 22/02/2017
Effective start: 22/02/2017
Expected end: 03/02/2020
Effective end: 22/01/2020

Type

Theme

Territory

Entities

Planning body
ENTE NAZIONALE PER L'AVIAZIONE CIVILE ENAC
Implementing body
AEROPORTI DI PUGLIA SOCIETA PER AZIONI IN SIGLA SPA
Beneficiary
AEROPORTI DI PUGLIA SOCIETA PER AZIONI IN SIGLA SPA
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Contribuire alla realizzazione di un sistema logistico nazionale, supportando la costruzione di una rete nazionale di terminali di trasporto e di logistica, integrata, sicura, interconnessa ed omogenea

Programming area

2007-2013 Cohesion Action Plan
2007-2013 Cohesion Action Plan
Programme
PROGRAMMA PAC MINISTERO DELLE INFRASTRUTTURE E TRASPORTI - SALVAGUARDIA INTERVENTI
Line
Salvaguardia
Action
lnterporto di Marcianise. Strada di collegamento

Other projects in territory