CUP: F81B10001480001
ADEGUAMENTO AL TIPO ABA (4 CORSIE) DELLAITINERARIO SASSARI A OLBIALOTTO 2
SUMMARY OF THE PROJECT
ADEGUAMENTO AL TIPO ABA (4 CORSIE) DELLAITINERARIO SASSARI A OLBIALOTTO 2
Implementation indicator
Estensione in lunghezza
- Target
- 12.40 km
- Achieved
- 10.79 km
Funding monitored
€ 116,310,917.49
of which cohesion funds
€ 116,310,917.49
Given name | Amount |
---|---|
Development and Cohesion Fund | 116310917.49 |
- Economies:
- € 35,459,082.51
Payments monitored
€ 69,040,916.52
of which cohesion funds
€ 69,040,916.52
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2013 | 29813.74 | 29813.74 | 0 |
2014 | 908330.55 | 938144.29 | 0 |
2015 | 3165928.77 | 4104073.06 | 3 |
2016 | 164800.93 | 4268873.99 | 3 |
2017 | 3724293.81 | 7993167.80 | 6 |
2018 | 263116.22 | 8256284.02 | 7 |
2019 | 3195250.51 | 11451534.53 | 9 |
2020 | 19116861.90 | 30568396.43 | 26 |
2021 | 17424695.09 | 47993091.52 | 41 |
2022 | 16812586.43 | 64805677.95 | 55 |
2023 | 4235238.57 | 69040916.52 | 59 |
State of progress
Open
Expected start: 23/02/2017
Effective start: 23/02/2017
Expected end: 27/01/2024
Effective end: not available
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- REGIONE AUTONOMA DELLA SARDEGNA
- Beneficiary
- REGIONE AUTONOMA DELLA SARDEGNA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SARDEGNA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario
Other projects in territory
Same theme
ADEGUAMENTO AL TIPO ABA (4 CORSIE) DELLAITINERARIO SASSARI A OLBIA. LOTTO 1 | € 81,592,659 |
MIGLIORAMENTO SISTEMA VIARIO RURALE ACCESSO LOCALITA' 'BINZANA' | € 361,520 |
COMUNE DI ARDARAACQUISTO VE | € 40,000 |
Same type of investment
ADEGUAMENTO AL TIPO ABA (4 CORSIE) DELLAITINERARIO SASSARI A OLBIA. LOTTO 1 | € 81,592,659 |