CUP: B57B15000390003
AREA DI LAMINAZIONE DEL T. SEVESO
SUMMARY OF THE PROJECT
AREA DI LAMINAZIONE DEL T. SEVESO
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Funding monitored
€ 38,698,119.59
of which cohesion funds
€ 38,698,119.59
Given name | Amount |
---|---|
Development and Cohesion Fund | 38698119.59 |
Payments monitored
€ 1,101,639.99
of which cohesion funds
€ 1,101,639.99
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 23895.23 | 23895.23 | 0 |
2016 | 118678.68 | 142573.91 | 0 |
2017 | 578963.12 | 721537.03 | 1 |
2018 | 143974.59 | 865511.62 | 2 |
2019 | 236128.37 | 1101639.99 | 2 |
State of progress
Open
Expected start: 15/09/2024
Effective start: not available
Expected end: 30/09/2025
Effective end: not available
Entities
- Planning body
- REGIONE LOMBARDIA
- Implementing body
- AGENZIA INTERREGIONALE PER IL FIUME PO AIPO
- Beneficiary
- AGENZIA INTERREGIONALE PER IL FIUME PO AIPO
- Executor
- AGENZIA INTERREGIONALE PER IL FIUME PO AIPO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico
Other projects in territory
Same theme
AREA DI LAMINAZIONE DEL T. SEVESO | € 0 |
Same type of investment
BANDA ULTRALARGA NELLE AREE BIANCHE DEL TERRITORIO DELLA REGIONE LOMBARDIA CON FONDI FSC | € 196,866,863 |
AREA DI LAMINAZIONE DEL T. SEVESO | € 0 |